Posted By Unipiles in Uncategorized / Apr 29, 2017 /
Transferring all underground water from project site to the sea through a 6.0 KM open channel and pumping stations
Posted By Unipiles in Uncategorized / Mar 19, 2017 /
Executing of Dewatering Works for Area 1 with Appx. area of 1 Million
M2 Amount of water required to be transferred is Appx. 2.5 Million
M3 of water over a duration of 3 Months 42 Dewatering Pumps will be utilized to execute the job after conducting a pumping test and determining the most appropriate type of pump to be utilized in such a project.
Posted By Unipiles in Uncategorized / Jun 07, 2016 /
Underproduction in Abdali area is labours camp to accommodate Appx. 3,000 Labours. Scope is to drill water wells for the purpose of water production thus feeding R.O system to produce drinkable water for labours.
Posted By Unipiles in Uncategorized / Jun 01, 2016 /
Project has been subcontracted through First United Gen. Trading and Contracting Co. who are appointed by M/S First Kuwaiti for Educational Services as package I contractor for Enabling works. Unipiles Scope Includes: Shoring for 10 M Deep Dewatering using deep wells system Water Treatment
Posted By Unipiles in Uncategorized / Mar 28, 2016 /
Phase I Enabling Works including Work Permits Temp. Fences and Stock Piling Excavation Shoring Dewatering Project Features: Area: 22,500 M2 Depth: 18.25 M Execution Duration including Piling: 400 Days